Hi All,
I have this issue with planning and exception in MD04/MD06
There is for a raw material ,with MRP type P1 and time fence=30 days.
Scheduling agreement has planned delivery as 30 days and GR proc time=1 day
Post MRP run looking at MD04 ,there are no exception message shown for existing firmed scheduling agreement dated 2nd Oct 2015 ,
even though we are going negative on 30th Sep 2015
Is it standard behavior in time fence ? if not please let me know ,the settings to be validated